Planning the Project

Image result for technology in project management

 

Corporations of varying sizes and operations within the construction industry acclaim the contribution of project management applications that assist in business and operational practices. An integrated intelligent construction management application that enables process modeling and algorithmic analysis of construction process planning, interacts with a mainframe-based automated relational database system, and drives the project sequencing, scheduling, decision making and change management processes can introduce dramatic speed, simplicity, accuracy, and collaboration into existing project planning practices.

 

The project management techniques related to the project planning phase include

  1. Describing project scope, alternatives, and feasibility. The understanding of the content and complexity of the project. Some relevant questions that should be answered include:
    • What problem/opportunity does the project address?
    • What results are to be achieved?
    • What needs to be done?
    • How will success be measured?
    • How will we know when we are finished?
  2. Divide the project into tasks. This technique is also known as the work breakdown structure. This step is done to ensure an easy progression between tasks.
  3. Estimating resources and creating a resource plan. This helps to gather and arrange resources in the most effective manner.
  4. Developing a preliminary schedule. In this step, you are to assign time estimates to each activity in the work breakdown structure. From here, you will be able to create the target start and end dates for the project.
  5. Developing a communication plan. The idea here is to outline the communication procedures between management, team members, and the customer.
  6. Determining project standards and procedures. The specification of how various deliverables are produced and tested by the project team.
  7. Identifying and assessing risk. The goal here is to identify potential sources of risk and the consequences of those risks.
  8. Creating a preliminary budget. The budget should summarize the planned expenses and revenues related to the project.
  9. Developing a statement of work. This document will list the work to be done and the expected outcome of the project.
  10. Setting a baseline project plan. This should provide an estimate of the project’s tasks and resource requirements